Hidroeléctrica de Cahora Bassa

2014 - 2015

Refurbishment of 32 Heat Exchangers and refurbishment of the “Cooling Tower” of HVDC thyristor tanks.

MOTRACO - Reactor being installed at the Maputo Substation (2011)

Massinga Substation (EDM) - Disconnectors Assembly (2016)

Songo Substation (HCB) - Installation of Smoothing Reactors (2014)

EDM Power Station Temane - 2 x 2.6MVA Gas powered Generators Installed by Tecnel (2015)

CLN / VALE - Installation of a Rural Transformation Station for a 33kV power line (2012)

Central Hospital of Maputo - Installation of generator set, switchboard and minisubstation

Projects

Our References

Installation of 3 x 107MVA HVDC 535 / 600kV Transformers

Hidroeléctrica de Cahora Bassa

2014 – 2015

Expansion of the Salamanga Substation 66/33kV

Electricidade de Moçambique

2014

Replacement of the 6 HVDC smoothing reactors 535 kV of the 2 Poles, with new and more modern coils.

Hidroeléctrica de Cahora Bassa

2012 - 2014

Supply of power lines and external lighting for camps A, B, C and for admin offices for the VALE’s Project.

Corredor Logístico Integrado de Nacala

(CLN)

2012 - 2014

Supply of permanent and emergency energy installations for CISM.

Centro de Investigação em Saúde de Manhiça (CISM)

2012

Reinforcement of the Medium Voltage Network of Maputo City

Electricidade de Moçambique

2011 - 2012

The Mozambique Transmission Company

(MOTRACO)

2011

Installation of 400kV AC Reactor