Other Work Performed

2016

  • Continuation of works initiated in 2015

  • Start of works at the new Lindela Substation

2015

  • Beginning of works on the new Macia Substation 275/110 kV - 250 MVA

  • Works begins on the new Massinga Substation 110/33kV - 30 MVA

  • Beginning of the works at the Maxixe Substation ​

Electricidade de Moçambique

Reinforcement and Expansion of EDM's National Transmission Network
Introduction

In 2015 EDM began work on the implementation of the significant project for "Reinforcement and Expansion of the National Transportation Network of EDM", comprising 4 packages: The main package and optional packages 1, 2 and 3.

Tecnel Service is the main subcontractor of the Consortium responsible for the Main Package, performing the following works: Assembly of the Substations comprising of all structures and equipment of High and Low Voltage, including Land Network and Control Equipment.

Work currently in progress (2016)

  • Assembly of structures and equipment comprising of High and Low Voltage, including Land Network and Control Equipment in the new Substations of Massinga and Macia and also in the existing Substations of Maxixe and Lindela.

© 2017 by Tecnel Service, Lda.

Av. das Indústrias, Parcela 760 

C.P. 99 - Machava

Maputo, Moçambique

Tel: +258 21 751 032

PABX: +258 82 / 84 365 7724

info@tecnel.co.mz

Audited by: